FOR COOs, VPs AND GENERAL MANAGERS

​

Plans that last past Wednesday​

Most mine plans are built from P50 rates for every department. When no department has the protective capacity to catch up after a shock, a P50 plan behaves like a much lower one. Your planners feel it first, re-cutting the plan every week. The owner feels it next, in guidance and the cost of capital.

SIGNS TO LOOK FOR

​

Signs your plan has no shelf life

​

Planners and superintendents know most of these. Few of them reach an executive dashboard.

​

  • The weekly plan is re-cut by Wednesday, most weeks.

  • Planning says operations will not follow the plan, and operations says planning writes fantasy schedules.

  • Your planners spend more of the week explaining variance than planning.

  • Experienced planners have left, and their spreadsheets and know-how left with them.

  • A bad week is recovered with overtime and weekend heroics, or not at all.

  • New scheduling software reports the risk more precisely, and the misses continue.

  • Production lands in the lower half of guidance more often than the upper half.

​

If three or more sound familiar, look at the capacity design underneath the plan before you look at the planners.

WHAT THE INDUSTRY SAYS

​

The planner shortage is real

​

A McKinsey survey of mining leaders found that 71 per cent say the talent shortage is holding back their production targets, and that mine planning is among the hardest fields to recruit. McKinsey also reports that Australian enrolments in mining engineering have fallen by about 63 per cent since 2014.

​

The usual answers are more graduates, skilled migration, better pay and better scheduling software. Each has its place. None of them changes the job the planner is asked to do. The loop below is our reading of how that job drives people out.

​

Mining leaders on the talent shortage

71% say it holds back production

​

Mines at or below the lower half of their own guidance range, over five years

60%

If guidance midpoints were true P50s, about half of mines would land there.

​

Sources: McKinsey & Company, Has mining lost its luster? (2023), survey of mining leaders; Accenture, The mining industry's $64 billion production gap (2025). The loop is our interpretation, and neither source tests it.

THE ARITHMETIC

​

Why a P50 plan behaves like a much lower plan

​

1 Each department plans to its average

​

In a balanced chain every department is resourced to the same average rate. On any given day, each has roughly an even chance of reaching it.

​

2 The mine needs all of them on the same day

​

With six departments in series and nothing in hand between them, all six reach their rate on about one day in 64. Our earlier article called this a P50 plan living in a P02 reality.

​

3 Lost time at the bottleneck stays lost

​

Operations science has a law for this. Hopp and Spearman's variability buffering law says variability is paid for with some mix of stock, capacity and time. Take out the stock and the protective capacity, and the mine pays in time. With no department able to run harder for a few shifts, the lost tonnes are never made up.

​

4 So the plan is re-cut

​

The plan is cut again by mid-week, and again the week after. Better scheduling software measures the risk accurately and still cannot remove it. Better maths cannot overcome bad physics.

Illustrative arithmetic. It assumes each department misses its rate independently, with nothing in hand between them. Real mines carry some stock between stages, which improves the odds; the mechanism is the same.

​

Protective capacity changes those odds. When the departments around the bottleneck can run harder for a few shifts, they refill the stock in front of it after a bad day, and one department's bad day stops being the mine's.

​

The design that produces the most looks the least efficient on a utilisation report.

​

See it for yourself in One mine, two scoreboards, a five-minute simulation.

THE COST OF A PLAN THAT BREAKS

​

Who pays when the plan breaks

​

The planner pays first, in the job itself. The owner pays later, in how the asset is financed and valued.

WHAT IT DOES TO PLANNERS

​

Accountable for a plan the mine cannot keep

​

  • A planner answers for plan attainment, while the capacity that decides it is set elsewhere, often in a cost review.

  • Burnout research has long linked exhaustion to that kind of mismatch between workload and control.

  • The knowledge that keeps a fragile mine running sits in spreadsheets and in people's heads, and it leaves when they do.

  • Each departure makes the next plan more fragile.

  • In our view, much of the planner attrition the industry reports starts here.

WHAT IT DOES TO THE OWNER

​

Unpredictable output costs more than the lost tonnes

​

  • Much of a mine's cost is fixed, so a small change in output moves EBITDA a long way.

  • Research across listed firms finds that more volatile cash flows go with lower investment and dearer outside capital.

  • The same body of research links steadier cash flows with higher market values.

  • Lenders increasingly test mine projects at 85 to 90 per cent of nameplate, and weight demonstrated performance above projections.

  • Missed guidance can bring stricter funding terms and discounted equity raisings.

  • In our view, a mine whose P50 behaves like a much lower plan ends up financed and valued as a smaller mine.

For owners and boards, the investment side is set out on Before buying more capacity, test the capacity you already own.

​

Steady output is worth more than the same tonnes delivered unevenly.

CASE: A NSW LONGWALL

​​

The same mine, before and after

​

TWO YEARS AFTER MOS

​

Wide swings, a budget out of reach

​

A NSW longwall had run a full MOS for two years, with the planning cascade, Leader Standard Work and meeting cadence all in place. Daily ROM averaged 9,612 tonnes against a budget of about 13,000, and swung widely from day to day.

​

Its best three days averaged 14,136 tonnes, so the installed system had already shown it could beat the budget on a good day.

​

Read the case study

​

PHASE 1 WITH A FLOW ROOM

​

A narrower band, closer to budget

​

A Flow Room was then added beside the MOS. In the first phase daily ROM averaged 12,047 tonnes, about 25 per cent higher, and the day-to-day swings narrowed. The gap between the average and demonstrated capacity fell from 32 per cent to about 15 per cent, with no conventional capacity project.

​

The mine came close to budget without reaching it. Once flow was stable, it became clear the budget asked more than the bottleneck could deliver, something nobody could see while output swung so widely.

​

In our experience, that narrower spread is what gives a weekly plan its shelf life.

​

In the chart below, orange is daily ROM two years after MOS and blue is phase 1 after the Flow Room was added. The red arrows show the gap between the average and demonstrated capacity.

​

Average daily ROM, phase 1 against the MOS baseline

+25%

From 9,612 to 12,047 tonnes a day, with no conventional capacity project.

​

Gap between average and demonstrated capacity

32% to 15%

Approximate, measured against the mine's best three days.

​

Our historical range

10 to 40%

Often within 12 weeks. Context from past work, never a forecast for your mine.

Daily run-of-mine tonnes at a NSW longwall: two years after MOS go-live the average was 9,612 tonnes a day against a budget of about 13,000; in phase 1 after a Flow Room was added the average rose to 12,047 tonnes a day and the swings narrowed

WHAT CHANGES

​

Fix the physics, then plan

​

The planning tools and the planners can stay. What changes is the system they plan.

​

In practice, four changes do most of the work.

1 Size the plan to the bottleneck

​

Name the stage that sets the mine's output. Daily and weekly plans match its demonstrated rate, and other work is paced so it neither starves nor blocks it.

​

2 Name the protective capacity

​

The spares, stockpiles and crew time around the bottleneck are labelled and agreed with finance, so they survive the next cost review.

3 Give the next 48 hours an owner

​

Department heads meet for 30 minutes a day in a Flow Room beside your MOS, and settle cross-department calls in the room.

​

4 Then let stochastic planning tune the plan

​

Once the chain absorbs ordinary shocks, probabilistic tools set buffers and sequences. For your planners, the plan gets a shelf life and re-planning becomes the exception.

BEFORE THE NEXT BUDGET

​

Questions to put to your team

​

These are worth answering before you approve the next plan. A good answer to each is short and specific to your site.

​

  • How many weekly plans last quarter were re-cut before Wednesday?

  • On what share of days did the bottleneck reach its planned rate?

  • Where does the budget sit in your daily production record: near the median day, or well above it?

  • How many planners have left in the last two years, and what did they say on the way out?

  • Which spares, stockpiles or crew time were removed in the last cost review?

WORKING WITH STRATFLOW

​

A contained first look at one operating asset

​

Each step is small, and you decide after each one whether to go on. If the work goes ahead, it runs through a daily Flow Room beside your existing management operating system. Department heads meet for about 30 minutes each morning to look at the bottleneck and its buffers, and settle cross-department calls in the room.

​

Through many interventions we have found that in the absence of a Flow Room, the gains fade. Our part is deliberately small. The site team does the work and keeps the result.

1

​

Check the gap

​

Run the Best-Day Diagnostic on six months of daily production. The calculation stays in your browser.

2

​

Talk it through

​

A 30-minute confidential call about the gap, the bottleneck and what your plan assumes.

3

​

Five days on site

​

A discovery with your site team to find the bottleneck and see how the plan treats it.

4

​

Decide

​

A go or no-go decision before any wider commitment. If it is a go, the Flow Room starts beside your existing routines.

EVIDENCE AND LIMITS

​

Held to what it shows

​

The workforce and guidance figures on this page come from published surveys and reports, listed below. The link we draw between capacity design and planner attrition is our interpretation, and none of those sources tests it. The buffering law is established operations science, and the six-department arithmetic is illustrative, with its assumptions stated. The longwall result is case evidence, not a controlled trial, and our historical range is context, never a forecast. Production results are not safety results, and we report safety measures separately.

​

The method was developed by the late Arrie van Niekerk over more than 20 years and more than 90 mining interventions. Hendrik Lourens, FAusIMM, COHSProf and TOCICO certified, trained under him and has applied it in eight interventions over 12 years.

NEXT STEP

​

Find out how much your plan can carry

​

Run the diagnostic on your own data today, or talk through one operating asset with us. Either way you will see how far your everyday production sits below what your mine has already shown it can do.

RELATED READING

​

On this site

​

Green departments, red mine

Why a sound management operating system still stalls, and the daily routine that sits beside it.

​

More capital, or a lower target?

How to point existing capital at the bottleneck, with a payback calculator.

​

Lean, OEE and the tonnes between departments

Why efficiency programmes remove the stock and protective capacity that keep a plan on track.

​

One mine, two scoreboards

A five-minute simulation of a mine where every department reports green.

​

Why your P50 mine plan breaks by Wednesday

The original article on stochastic planning and brittle mines.

​

​

Figures marked illustrative are examples only, not forecasts for any site. Sources: McKinsey & Company, Has mining lost its luster? (2023); Accenture, The mining industry's $64 billion production gap (2025); Minton and Schrand, Journal of Financial Economics (1999); Rountree, Weston and Allayannis, Journal of Financial Economics (2008); Gilbert + Tobin (2025); Skillings Mining Review (2026); Maslach and Leiter (1999) on burnout; Hopp and Spearman, Factory Physics.